Procurement guide
A disciplined way to buy commercial energy storage.
Eight stages, written for the person who has to justify the decision internally. No vendor names, no estimated savings, no assumed incentives — just the sequence that keeps quotations comparable and the assumptions visible.
Method
The eight stages.
01
Establish why you want storage
02
Define discharge power, then duration
03
Convert to requested delivered energy
04
Document the site honestly
05
Clarify the grid connection position
06
Fix the timeline and the decision path
07
Issue one identical brief to every supplier
08
Compare only written figures, attributed by name
Worked example
How the delivered-energy calculation works.
Requirement stated by the owner
Discharge power = 500 kW
Discharge duration = 4 hours
500 kW × 4 h = 2,000 kWh
2,000 kWh ÷ 1,000 = 2.0 MWh
If the owner had entered 2 MW × 4 h: 2,000 kW × 4 h = 8,000 kWh = 8.0 MWh
What this figure is not.
It is not the battery you will buy. Real systems lose energy to conversion and thermal management, reserve capacity for depth-of-discharge limits, and fade over their life. Those factors are product-specific, so the supplier — not us — states the nameplate and usable capacity required to deliver your requested energy in year one and in the final warranty year.
Question bank
Eight questions suppliers should answer in writing.
Sizing
What nameplate power and usable energy do you propose to deliver our stated kW and hours, and what efficiency, depth of discharge and end-of-life assumptions are inside that?
Performance
How is round-trip efficiency measured, at what state of charge and temperature, and does the stated figure include auxiliary loads and thermal management?
Warranty
What is the warranty term, what throughput or cycle limit applies, what performance floor is guaranteed, and what voids it?
Scope
What exactly is inside your price — enclosure, transformer, switchgear, protection, civil works, interconnection, commissioning, spares, training? Name what is excluded.
Schedule
What is the lead time from order, what sequencing do you assume on site, and what are the liquidated consequences of delay?
Service
Who attends a fault, in what response time, for how many years, and at what escalating cost after the initial term?
Grid
Which interconnection tasks are yours and which are ours, and what happens commercially if the utility imposes a condition neither of us assumed?
End of life
Who owns decommissioning, recycling and residual value, and what is assumed in your figures?
Put your own numbers through it
The configurator applies this sequence and produces the brief for you.